Management comes clean. MAHB, at an analyst briefing yesterday, revealed
the latest development of KLIA2. In a nutshell, the project size is
much bigger than originally planned with a capacity of 45m (versus 30m,
+50% increase), completion date has been pushed to Apr 2013 (previous
Oct 2012) and the project cost has soared to RM3.6-3.9b (versus
RM2.0-2.5b, +56%-80% increase). Management asserts new IRR of >10%
(our original estimate 13.2%). We are assessing the impact to our
earnings model and place MAHB under review.
Maybank research (30 November 2011)